The correct answer is A. Project schedule.
The project schedule is a document that outlines the timeline for completing all the tasks and activities involved in a project. It includes information such as the start and end dates for each task, the dependencies between tasks, and the resources assigned to each task. Therefore, a project manager can find information on the resources assigned to a particular task in the project schedule. The project schedule is an important tool for managing the project, as it provides a roadmap for the project team to follow and helps ensure that the project stays on track and within budget.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CyberRooster
2 years, 2 months ago