Exam PK0-004 topic 1 question 72 discussion

Actual exam question from CompTIA's PK0-004
Question #: 72
Topic #: 1
[All PK0-004 Questions]

A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?

  • A. Project schedule
  • B. Cost plan
  • C. Scope statement
  • D. Impact assessment
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 156

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CyberRooster
2 years, 2 months ago
The correct answer is A. Project schedule. The project schedule is a document that outlines the timeline for completing all the tasks and activities involved in a project. It includes information such as the start and end dates for each task, the dependencies between tasks, and the resources assigned to each task. Therefore, a project manager can find information on the resources assigned to a particular task in the project schedule. The project schedule is an important tool for managing the project, as it provides a roadmap for the project team to follow and helps ensure that the project stays on track and within budget.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago