A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?
The necessary step to record the actual durations of the WBS work packages is to establish and set the baseline. Therefore, option B is the correct answer.
The project baseline includes the planned start and finish dates for all WBS work packages. Once the project is underway, the actual start and finish dates can be recorded and compared against the planned baseline dates to track progress and identify any deviations from the plan. This information is critical to help the project manager make adjustments to the schedule and resource allocations as necessary to keep the project on track.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CyberRooster
2 years, 2 months ago