A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements?

  • A. Sponsor
  • B. Project manager
  • C. Project management office
  • D. Project team
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 108

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CyberRooster
2 years, 2 months ago
The BEST source for high-level project requirements is the sponsor. Therefore, option A is the correct answer. The project sponsor is the person or group that initiates the project and provides the funding and resources necessary for the project's success. They are responsible for defining the project's business objectives and ensuring that the project aligns with the organization's strategic goals. As such, they are the best source for high-level project requirements as they can provide the necessary context and insight to ensure that the project charter reflects the organization's needs and goals.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago