A project in the execution phase is over budget, and tasks on the critical path are on schedule. Which of the following should the project manager do NEXT?
Since the project is over budget, it is necessary to take corrective action to address this issue. Issuing a change request is an appropriate step to take in order to formally request changes to the project scope, schedule, or budget, and to assess the impact of those changes on the project baseline. Updating the project management plan, revising the project charter, and evaluating the impact to the baseline may also be necessary, but these steps would typically follow the issuance of a change request.
Since the project is over budget, the next step the project manager should take is to evaluate the impact to the baseline. Therefore, option D is the correct answer.
The project baseline is the approved project plan that includes the scope, schedule, and budget. When the project is over budget, the project manager needs to determine the cause of the variance and evaluate the impact to the baseline. This evaluation will help the project manager determine the necessary actions to take to bring the project back on track.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
6phaeton
2 years agoCyberRooster
2 years, 2 months ago