Scenario: A Citrix Engineer is managing a Provisioning Services Farm with the following specifications:
- A single Farm with one Site, with two Provisioning Services servers deployed with 8 vCPU each, which are supporting a total of 500 target devices in production.
-The ports and threads have been configured so that each server can stream concurrently to 250 devices each.
-Due to an upcoming merger, 250 more target devices must be supported by the existing Provisioning Services farm.
-The Provisioning Services servers must handle the extra capacity while aligning to Citrix leading practices for resiliency.
Which step should the engineer perform to accomplish these requirements?