exam questions

Exam 350-601 All Questions

View all questions & answers for the 350-601 exam

Exam 350-601 topic 1 question 186 discussion

Actual exam question from Cisco's 350-601
Question #: 186
Topic #: 1
[All 350-601 Questions]

The EPLD update of the supervisor module has been scheduled for several Cisco MDS 9000 Series Switches. What will be the impact of the update?

  • A. All traffic is stopped for the duration of the EPLD update and the switch is rebooted after the upgrade is completed.
  • B. The redundant supervisor takes over while the EPLD update is in progress and the switch is rebooted after the upgrade is completed.
  • C. All control plane traffic is stopped for the duration of the EPLD update and the switch remains operational for the duration of the upgrade.
  • D. The redundant supervisor takes over while the EPLD update is in progress and there is no service disruption.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
bizzar7774
3 weeks, 3 days ago
Selected Answer: A
All traffic is stopped for the duration of the EPLD update, and the switch is rebooted after the upgrade is completed. Explanation: An EPLD update on the supervisor module of Cisco MDS 9000 Series Switches is a disruptive process that affects both control and data plane operations. Traffic Disruption: During the EPLD update, all traffic—both control plane (management and protocol operations) and data plane (data forwarding)—is halted. Switch Reboot: After the EPLD update is completed, the switch undergoes a reboot to apply the changes effectively.
upvoted 1 times
...
wickkkkkkkkkkkkkkkkkk
4 months, 2 weeks ago
DDDDDDDDDDDDDDDD
upvoted 1 times
...
Scheldon
1 year, 2 months ago
Selected Answer: A
Official Cert Guide Book p503 " NOTE An EPLD update of the supervisor module of fabric switches (Cisco MDS 9100, Cisco MDS 9200, and Cisco MDS 9300 Series switches) is disruptive because there is no redundant supervisor to take over while the update is in progress. All traffic through the system is stopped for the duration of the update, and the switch is rebooted after the upgrade has completed. The update may take up to 30 minutes to complete. "
upvoted 1 times
...
GuyThatTakesDumps
1 year, 9 months ago
Selected Answer: A
I will chose A
upvoted 2 times
...
mendieta
2 years, 3 months ago
For me answer is D. https://www.cisco.com/c/en/us/td/docs/switches/datacenter/mds9000/sw/6_2/release/notes/epld/epld_rn.html#62980
upvoted 1 times
...
Manu_75
2 years, 3 months ago
Selected Answer: A
I would answer A. Question mentions 9000 Séries “Switches”, not “Directors”. Also, even with a redundant sup, you need to upgrade the standby from the active, then failover and upgrade the other sup. The supervisor does not “take overl by itself.
upvoted 1 times
cypher9
2 years ago
Correct
upvoted 1 times
...
...
Dodono
2 years, 3 months ago
This is very tricky question. There is no informations if the MDS switches are 9100/9200/9300 or 9500/9700. If MDS9100/9200/9300 then the answer is A (because there is no redundant supervisor module),. But if it is about MDS9500/9700 then the correct answer is D(because they have redundant supervisor)
upvoted 1 times
corelate_9
2 years, 3 months ago
option D said, Service disruption, not traffic disruption
upvoted 1 times
...
...
RTL_dude
2 years, 5 months ago
Selected Answer: D
I think it is D. The question doesn't define the exact switch type. It *is* disruptive for MDS 91/92/93xx series switches, which don't have standby supervisors, but for director switches, the upgrade is non-disruptive if the standby supervisor is upgraded first. The answers seem to imply that we have switches with a standby supervisor units. https://www.cisco.com/c/en/us/td/docs/switches/datacenter/mds9000/sw/8_x/release_notes/epld/epld_rn_8x.html#pgfId-314100
upvoted 4 times
...
kiluahxh
2 years, 7 months ago
Selected Answer: A
An EPLD update of the supervisor module of Fabric Switches (Cisco MDS 9100, Cisco MDS 9200, and Cisco MDS 9300 Series switches) is disruptive since there is no redundant supervisor to take over while the update is in progress. All traffic through the system is stopped while updating and the switch is power cycled after the upgrade has completed. The update may take up to 30 minutes to complete.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago