Question #: 47
Topic #: 1
[All 300-625 Questions]

A storage engineer is troubleshooting a Cisco MDS switch upgrade issue. What prevents the completion of a non-disruptive upgrade?

  • A. The Fibre Channel host initiator is connected.
  • B. The Fibre Channel storage target is connected.
  • C. The Cisco Fabric Services operation in progress.
  • D. The Fibre Channel and FCoE storage targets are connected.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://www.cisco.com/en/US/docs/storage/san_switches/mds9000/sw/rel_3_x/release/notes/14116.16.html

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
saulvedis
3 years, 6 months ago
Answer: C
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.