In Cisco SD-WAN, which protocol is used for control connections between Cisco SD-WAN devices?

  • A. BGP
  • B. DTLS
  • C. OSPF
  • D. OMP
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TheNetworkStudent
Highly Voted 2 years, 10 months ago
In the reference link under the 'Control Plane Authentication' part, you can find the following: Then, during the automatic authentication process, as pairs of devices (routers and controllers) are establishing DTLS control connections, each device compares the serial numbers (and for routers, the chassis numbers) to those in the files installed on the router. DTLS is the connection that facilitates the exchange of OMP information between the devices. In vManage the number of control connections also shows the amount of DTLS connections to/from a device. OMP is not the control connection, it's the control plane management protocol. B is correct, DTLS
upvoted 9 times
...
Mykhey
Most Recent 1 month, 4 weeks ago
Both DTLS and OMP are true since the specific devices have not been mentioned! The wording of the question should be reviewed
upvoted 1 times
...
elninio13
8 months ago
Why the owners dont correct the answers???
upvoted 2 times
...
ChrisCCNA
1 year, 9 months ago
Selected Answer: B
B due to the way the question is asked. Poor wording. If it said exchange routing information then I'd say omp.
upvoted 2 times
...
khanda
2 years, 2 months ago
Selected Answer: B
DTLS is correct
upvoted 1 times
...
Nyck
2 years, 3 months ago
"which protocol is used". Otherwise they would have said : Routing protocol. So, DTLS is the only one possible. B
upvoted 1 times
MerlinTheWizard
1 year ago
Dont be so sure they would have said it like that.. questions are written by global community participating in the Cisco SME program and not dedicated Cisco employees anymore. Typos and other mistakes are often overlooked when reviewing the questions before they are released into the exam pool
upvoted 1 times
...
...
A_Wolf
2 years, 4 months ago
Selected Answer: B
DTLS – between vSmarts, vManage and vBond permanently DTLS – between vSmart to vEdge permamently (DTLS or TLS). DTLS – between vBond to vEdge temporarily during vEdge onboarding. OMP – Only carries routing information between vSmart and vEdges and vSmart to vSmart vBond orchestrators always use DTLS tunnels to establish control connections with other devices, so they always use UDP. The UDP port is 12346
upvoted 2 times
...
Speirsington
2 years, 6 months ago
DTLS: "vpn 0 interface tunnel-interface control-connections—Attempt to establish a DTLS or TLS control connection for a TLOC (on vEdge routers only). This is the default behavior. " https://www.cisco.com/c/en/us/td/docs/routers/sdwan/command/sdwan-cr-book/config-cmd.html#wp4894365670
upvoted 2 times
...
CCNPWILL
2 years, 6 months ago
Not a good question. I would go with B though. vManage directly to edge device is NOT OMP for example when distributing a localized policy. All devices have at minimum DTLS connection to one another. Excluding the vBond after the edge gets authenticated.
upvoted 1 times
...
CesarVergaraGalindo
2 years, 9 months ago
B is correct
upvoted 4 times
...
isaacmejia
2 years, 11 months ago
A simple "show control connection" from a Vedge will answer this question, in my opinion is taking about connection from vedges to controlllers, So we are taking DTLS
upvoted 2 times
...
mithradel
3 years, 1 month ago
OMP (Overlay Management Protocol)—The OMP protocol is a routing protocol similar to BGP that manages the Cisco SD-WAN overlay network. OMP runs inside DTLS control plane connections and carries the routes, next hops, keys, and policy information needed to establish and maintain the overlay network. OMP runs between the Cisco vSmart Controller and the vEdge routers and carries only control plane information. The Cisco vSmart Controller processes the routes and advertises reachability information learned from these routes to other vEdge routers in the overlay network.
upvoted 2 times
...
Maddy80
3 years, 1 month ago
The control connection means " Vsmart to Vedge " Communication , so OMP is the correct Answer .
upvoted 2 times
Mr_Cipher
2 years, 11 months ago
Agree. The keyword is "CONTROL". OMP is the one.
upvoted 1 times
Nalla123
1 year, 9 months ago
There is a difference between Control Connection and Control Protocol...
upvoted 1 times
...
...
...
Almanac
3 years, 2 months ago
DTLS is also a valid answer. because OMP is only running between vSmart to vSmart and vEdge to vSmart not across SD-WAN Devices.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago