This ensures that the active management server remains operational while the standby server is upgraded first. Once the standby server is successfully upgraded and verified, the active server can then be upgraded, minimizing downtime and maintaining high availability.
In Management High Availability, make sure the Primary Security Management Server is upgraded and runs, before you start the upgrade on other servers.
https://sc1.checkpoint.com/documents/R81/WebAdminGuides/EN/CP_R81_Installation_and_Upgrade_Guide/Topics-IUG/Upgrading-SecMmgt-Servers-in-Mmgt-HA-from-R80_20-and-higher.htm
Step Instructions 7
It should be D,
"In Management High Availability, make sure the Primary Security Management Server is upgraded and runs, before you start the upgrade on other servers."
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
7c2833a
5 days, 22 hours agokeikei1228
1 month agoyeru
3 weeks, 4 days agolironzruya7
7 months, 3 weeks agoKuKuKu83
10 months, 1 week agoRajeshkashi
10 months, 1 week ago