What is the PERT estimate of time for cable placement on a given job? - Optimistic time is 100 hours - Most likely time is 125 hours - Pessimistic time is 210 hours
TDMM page 21-23 (1554)
PERT formula is [Optimistic + (4 x Most likely) + Pessimistic] / 6
PERT = [100h + (4 x 125h) + 210h] / 6
PERT = 135h