What is the PERT estimate of time for cable placement on a given job?
- Optimistic time is 100 hours
- Most likely time is 125 hours
- Pessimistic time is 210 hours

  • A. 100 hours
  • B. 125 hours
  • C. 135 hours
  • D. 155 hours
  • E. 175 hours
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CUB90
1 year ago
TDMM page 21-23 (1554) PERT formula is [Optimistic + (4 x Most likely) + Pessimistic] / 6 PERT = [100h + (4 x 125h) + 210h] / 6 PERT = 135h
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago