What is the PERT estimate (in hours) for project design where: - Optimistic time is 40 hours - Most likely time is 50 hours - Pessimistic time is 60 hours
TDMM page 21-23 (1554)
PERT formula is [Optimistic + (4 x Most likely) + Pessimistic] / 6
PERT = [40h + (4 x 50h) + 60h] / 6
PERT = 50h
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CUB90
1 year ago