A conduit run is installed from the ER to a TR. It has two (2) 90 degree bend and a length of 20 m (65 ft). What will be the MINIMUM test rating of the pull cord left in the conduit?
TDMM page 12-40 (page 1025)
Provide a plastic or nylon line with a minimum test rating of ~90 kg (200lb) pulling tension in all entrance conduits.