A project manager has stated that he wants 'secure and controlled access to documentation, as well as support for impact analysis and traceability in terms of version history'.
What element of requirements management will offer this?

  • A. Change control
  • B. Configuration control
  • C. Configuration management
  • D. Software support
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Nekan
5 months, 3 weeks ago
Selected Answer: C
The correct answer is configuration management. Change Control deals with the processes and rules to follow in making amendments to project variables.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.