Exam RE18 topic 1 question 7 discussion

Actual exam question from BCS's RE18
Question #: 7
Topic #: 1
[All RE18 Questions]

Spicer, an herbs and spices company, is building a new website to grow its business online. A meeting is taking place to prioritize the requirements for inclusion in the first release of the website, which will take place in July. The second release of the website is planned for September.
Miranda, the company buyer is the owner for a requirement that states: 'The system shall provide screens for adding new products'. Miranda informs the meeting that new products are added to the system every three months and that she needs this functionality to be in place before the system goes live. In her view, it is a mandatory requirement.
Peter, who is developing the system, has stated that he can do a one-off upload of all the products into the database ready for launch in July, meaning that the website can initially go live without the 'add new product' functionality.
What priority is Miranda's requirement for the July release?

  • A. Could have
  • B. Must have
  • C. Should have
  • D. Want to have
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
KrutikaB
4 months, 3 weeks ago
Option C: Must Have: The requirement must be included in the first release to ensure it delivers the intended value. If this requirement is not added in the first release, the expected value will not be achieved. Should Have: The requirement should be included, but it is acceptable if it is not part of the first release, as it does not affect the overall system's functionality or value. According to the Miranda requirement, this feature is essential, but it can be deferred to the second release if necessary.
upvoted 1 times
...
queenedward9
7 months, 3 weeks ago
answer is C
upvoted 1 times
...
Nekan
11 months, 4 weeks ago
Selected Answer: C
For the July release, Miranda's requirement is a "should have." "Must have" requirements for July release are those that the development cannot do without. Since Miranda's requirement is going to wait till the next release, then it is a "should have" as of now, in the sprint leading to the second release, it would be a "must have."
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago