Exam RE18 topic 1 question 3 discussion

Actual exam question from BCS's RE18
Question #: 3
Topic #: 1
[All RE18 Questions]

A business analyst has collected the following legal requirement in support of a project seeking to improve the services provided by a children's charity:
The system must record all the details of the children and young people we interact with.
The project is in the early phases of requirements elicitation. At this stage, the business analyst is trying to ensure that they have captured the broad requirements.
Which style of requirements document is the business analyst constructing, and what additional (essential) attribute will they need to record?

  • A. Requirements catalogue; owner
  • B. Requirements catalogue; requirement ID
  • C. Requirements list; business area
  • D. Requirements list; source
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Nekan
5 months, 3 weeks ago
Selected Answer: D
At the early stage of requirements elicitation, a list would suffice. It is important to document the source of the requirement as well. A catalogue would be formed much later as the process progresses and requirements are refined.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago