Question #: 56
Topic #: 1
[All ACP-100 Questions]

You receive workflow configuration requirements for issues in the Closed status. They are as follows:
✑ Users must NOT be able to edit issues in this status.
✑ Jira administrators must be able to edit issues in this status.
✑ Only users in the release-managers group should see the transition to the Re-opened status
Which combination of two workflow configuration items should you use to meet these requirements? (Choose two.)

  • A. Properties
  • B. Post functions
  • C. Conditions
  • D. Validators
  • E. Triggers
Show Suggested Answer Hide Answer
Suggested Answer: CD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
RJ_Mikey
4 weeks, 1 day ago
Selected Answer: AC
A and C. Validators technically don't hide actions, they cancel it after it has been started.
upvoted 1 times
...
Sia_aws
1 year, 3 months ago
It should be A and C
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago