exam questions

Exam ACP-100 All Questions

View all questions & answers for the ACP-100 exam

Exam ACP-100 topic 1 question 34 discussion

Actual exam question from Atlassian's ACP-100
Question #: 34
Topic #: 1
[All ACP-100 Questions]

An issue is showing the Time Tracking section as follows:

There is clearly an hour's difference between the Original and Remaining estimates.
Identify two possible reasons Logged Time is showing as Not Specified. (Choose two.)

  • A. Time tracking was not enabled when the work was logged.
  • B. The remaining estimate was adjusted without logging any effort.
  • C. The hour's work was logged via a REST call by the user.
  • D. The work log would have exceeded the project's time allowance, so it cannot be counted.
  • E. The original estimate was increased.
  • F. You do not have view permission to see the logged work.
Show Suggested Answer Hide Answer
Suggested Answer: AB 🗳️
Reference:
https://confluence.atlassian.com/adminjiraserver/configuring-time-tracking-938847808.html

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
DdaG
1 month, 2 weeks ago
Selected Answer: AB
I think it is A, B
upvoted 1 times
...
cloudstudy12358
10 months ago
The answers I chose were B, E
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago