Question #: 36
Topic #: 1
[All CQE Questions]

During the performance of an audit, which of the following are key considerations?
I. What sampling plans may be necessary?
II. Is the audit schedule progressing as planned?
III. Is there a need for a technical specialist?
IV. Is the level of compliance satisfactory?

  • A. I, II and III only
  • B. II and IV only
  • C. I and IV only
  • D. I, II, III and IV
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
jdubiota
1 week ago
Selected Answer: D
doesn't it include all?
upvoted 1 times
...
Sachindra_89
1 year, 11 months ago
Selected Answer: B
Audit should be planned and compliance give according to observation, which is acceptable by auditors.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.