Actual exam question from ASQ's CQE
Question #: 14
Topic #: 1
[All CQE Questions]

Which of the following are likely to be positive actions in obtaining a supplier's commitment to quality improvement?
I. Involving the supplier early in the product development stage.
II. Partially reimbursing the supplier, when the product is rejected.
III. Establishing a firm schedule of required product quantities and dates.
IV. Providing meaningful and timely quality performance feedback.

  • A. I and IV only
  • B. I, II and IV only
  • C. I, III and IV only
  • D. I, II, III and IV
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Sachindra_89
5 months ago
Selected Answer: C
Partially Reimbursement supplier is not required when products is rejected.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago