Question #: 393
Topic #: 1
[All CMQ-OE Questions]

Rank in order, from first to last, the following steps in the supplier certification process.

1. Monitor performance
2. Develop criteria and process
3. Report results and award certification
4. Evaluate suppliers

  • A. 2, 4, 3, 1
  • B. 2, 1, 3, 4
  • C. 4, 2, 1, 3
  • D. 4, 1, 2, 3
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
4f400d2
1 week, 5 days ago
Selected Answer: A
The correct answer is A. Refer to ASQ CMQ/OE Page 527: Supplier Certification.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel