Exam CMQ-OE topic 1 question 191 discussion

Actual exam question from ASQ's CMQ-OE
Question #: 191
Topic #: 1
[All CMQ-OE Questions]

A company is considering converting a portion of its existing manufacturing space to storage in order to reduce dependence on an external warehouse. The following information reflects the results of a cost-benefit analysis.
Building construction changes$15,000

Reduced transportation$25,000 -
Manufacturing layout changes$36,000
Increased internal storage capacity$48,000
What is the total dollar benefit to be expected when the project is completed?

  • A. $48,000
  • B. $73,000
  • C. $76,000
  • D. $84,000
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
4f400d2
3 weeks, 1 day ago
Selected Answer: B
Sum of all benefits anticipated: Reduced transportation: $25,000 Increased internal storage capacity: $48,000 Calculating the total: $25,000 + $48,000 = $73,000. Therefore, answer B should be the correct answer. Answer C is computed by adding the following: Building construction changes: $15,000 Reduced transportation: $25,000 Manufacturing layout changes: $36,000. Why are the construction changes and layout changes considered benefits? Please let me know if I overlooked anything.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago