Actual exam question from Appian's ACD100
Question #: 10
Topic #: 1
[All ACD100 Questions]

Who is responsible for estimating the level of effort for Product Backlog items?

  • A. Product Owner
  • B. Testers
  • C. Developers
  • D. Scrum Master
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
albertcamu
4 months ago
Selected Answer: C
"The backlog of features is prioritized by the Product Owner and estimated by the Development Team. Then the most important features which can be completed are selected. By performing this detailed planning with each iteration, the team can react to new information, pulling in newly discovered, high-priority features. Iteration planning includes these activities" it's C!! from Step 1 https://community.appian.com/success/w/guide/2974/the-appian-delivery-methodology-part-ii
upvoted 1 times
...
Orestes96
4 months, 1 week ago
Selected Answer: D
Developer is the correct option
upvoted 1 times
...
Djoml1to
10 months ago
"The backlog of features is prioritized by the Product Owner and estimated by the Development Team. " Resource: https://community.appian.com/success/w/guide/2974/the-appian-delivery-methodology-part-ii
upvoted 3 times
...
PrettyA
10 months, 3 weeks ago
While testers (option B), Product Owner (option A), and Scrum Master (option D) are all essential roles in an Agile development team, the responsibility for estimating the level of effort for backlog items falls primarily on the developers, as they are the ones who will be implementing the functionality and have the technical knowledge to provide accurate estimates.
upvoted 1 times
...
Dhanushigan
1 year, 1 month ago
Selected Answer: A
it should be Product owner
upvoted 1 times
marcbernal
8 months, 1 week ago
No. Developers is the correct answer.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago