Question #: 452
Topic #: 1
[All CSCP Questions]

Which of the following components of advanced planning and scheduling (APS) defines and coordinates constraints?

  • A. Demand management
  • B. Resource management
  • C. Resource optimization
  • D. Resource allocation
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Wijitha
6 months, 1 week ago
Selected Answer: B
resource Management talk about capacity and constrains
upvoted 2 times
...
Rajiv8047
1 year ago
Selected Answer: C
Resource optimization is the component of advanced planning and scheduling (APS) that defines and coordinates constraints
upvoted 1 times
...
Hashha0s
1 year, 3 months ago
Selected Answer: B
Resource management. This module coordinates the capacities and constraints of resources across the supply chain. Inputs include planning objectives, demand management output, system constraints, customer data such as location, and costs, descriptions, and physical characteristics of products and resources.
upvoted 3 times
...
cscp2023
1 year, 10 months ago
I think is C
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...