Exam CSCP topic 1 question 284 discussion

Actual exam question from APICS's CSCP
Question #: 284
Topic #: 1
[All CSCP Questions]

The production scheduler for a bottleneck resource should:

  • A. schedule additional preventive maintenance for the resource.
  • B. ensure a constant queue of work waiting to be processed.
  • C. increase production lot sizes to increase utilization of resources.
  • D. implement pull signals for production of the bottleneck resource.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
cscp2023
1 year, 11 months ago
Theory of constrain
upvoted 1 times
...
gavini
2 years, 7 months ago
Selected Answer: B
WHY NOT b?
upvoted 1 times
gavini
2 years, 7 months ago
Sorry, i meant A*?
upvoted 1 times
Daesma
1 year, 4 months ago
Because if, in addition to being a bottleneck, we add more maintenance, it will be even more restrictive. The question also says nothing about reliability problems.
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...