Medium-term demand management projections are used primarily to:

  • A. complete strategic business planning of facilities.
  • B. complete forecasts at the item level.
  • C. aggregate demand for production planning.
  • D. develop the master production schedule.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
flyover11300
Highly Voted 2 years, 6 months ago
Answer should be C. A would be long term and D - MPS is on an item level, so would B and D be short term. S&OP produces production plan which is on aggregate level
upvoted 6 times
...
Jackie_K
Most Recent 1 year, 1 month ago
according to CSCP Book Long-term strategic needs, including long-term forecasting,product development, or capacity development Medium-term aggregate demand forecasting and sales and operations planning Short-term demand forecasting and item-level master scheduling Answer C is correct
upvoted 2 times
...
Prasathkmk
2 years ago
Answer should be D - master scheduling that is mps
upvoted 1 times
...
birdforest
2 years, 8 months ago
Think the Answer is D. C should be long term (S&OP)
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...