Answer should be C. A would be long term and D - MPS is on an item level, so would B and D be short term. S&OP produces production plan which is on aggregate level
according to CSCP Book
Long-term strategic needs, including long-term forecasting,product development, or capacity development
Medium-term aggregate demand forecasting and sales and operations planning
Short-term demand forecasting and item-level master scheduling
Answer C is correct
Think the Answer is D. C should be long term (S&OP)
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
flyover11300
Highly Voted 2 years, 6 months agoJackie_K
Most Recent 1 year, 1 month agoPrasathkmk
2 years agobirdforest
2 years, 8 months ago