Question #: 428
Topic #: 1
[All CSCP Questions]

A team has been given a project which requires them to design a new product with the following key performance indicators (KPIs) and prototype results:

What should be the next step of the project?

  • A. Close prototype phase and move to production phase
  • B. Stay in prototype phase and issue formal corrective action to address prototype yield only
  • C. Stay in prototype phase and issue formal corrective action to address all key performance indicators
  • D. Close prototype phase and move to production phase with verbal understanding that yield needs to increase
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
PMP1
Highly Voted 3 years, 1 month ago
why not B?
upvoted 12 times
...
Rajiv8047
Most Recent 1 year ago
Should be C
upvoted 1 times
...
Daesma
1 year, 4 months ago
Selected Answer: C
We have to remain in the prototype phase until all specifications are met. Right now we do not meet the "prototype yeld" but we must control that, as we improve this one, the others that are at the limit of the specification do not fall.
upvoted 4 times
...
saey
1 year, 6 months ago
Should be B
upvoted 2 times
...
cscp2023
1 year, 10 months ago
A is not correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...