The four risks of supply chain risk management are supply, demand:

  • A. quality, and process
  • B. value, and sustainability
  • C. process, and environmental
  • D. value, and environmental
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
seeralanb
Highly Voted 2 years, 10 months ago
it should be process and environmental
upvoted 9 times
...
trustabiodun
Highly Voted 2 years, 7 months ago
Yes! The four risks of supply chain risk management are supply, demand, Environmental and process risk
upvoted 5 times
...
Rajiv8047
Most Recent 6 months, 2 weeks ago
Selected Answer: C
Process, and environmental
upvoted 2 times
...
Rajiv8047
7 months, 3 weeks ago
Selected Answer: C
four risks of supply chain risk management are supply, demand, process, and environmental. There for answer was Process and environmental
upvoted 1 times
...
cscp2023
1 year, 6 months ago
Selected Answer: C
process + environmental
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago