In an assemble-to-order manufacturing environment, the master production schedule is typically the schedule of:

  • A. resources.
  • B. customer orders.
  • C. components and subassemblies.
  • D. the final assembly.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Sanjey
Highly Voted 3 years, 11 months ago
MPS may supply components and sub-assy but the schedule should show week wise final assembly
upvoted 5 times
...
GA301
Most Recent 9 months, 2 weeks ago
Selected Answer: D
According to Book : The focus of master scheduling in assemble-to-order is on scheduling the manufacture of the modules or components and on final assembly. In such cases, the efficient basis for the master production schedule is to schedule the limited number of components.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...