Which of the following inventory ordering techniques would a company's corporate warehouse utilize if it is interested in meeting both the quantity and timing requirements of demand from its regional warehouses?
A is the answer. DRP is the function of determining the need to replenish at branch warehouses using MRP logic against orders received at the branch warehouse. Kanban is a JIT pull system used on the warehouse floor that depends on visual cards or sign boards.
Since they mentioned inventory ordering techniques in the question, Kanban (Japanese for sign) is an inventory control system used in just-in-time (JIT) manufacturing to track production and order new shipments of parts and materials. I think Kanban is the right answer.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
nprestel
Highly Voted 4 years, 1 month agoOrb
Most Recent 2 years, 5 months agodailong142002
3 years, 1 month ago