Which of the following methods is used to minimize the bullwhip effect?

  • A. Outsourcing noncore business activities
  • B. Reducing the number of stock keeping units (SKUs)
  • C. Reducing lead time
  • D. Increasing factory inventory
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Explanation -
Demand-driven material requirements planning (DDMRP) is a relatively new type of ordering system that can be used for dependent and independent demand items at any point in the supply chain. DDMRP strategically positions inventory to achieve all the benefits of modern supply chain management (reduce inventory, lead times to the customer, and the bullwhip effect and increase customer service and asset usage efficiency) without needing to rely on safety stocks of finished goods or a pure make-to-order environment. Instead, DDMRP determines how to shrink total lead times by creating buffer inventories of key components that have longer lead times than other components making up a finished good.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
absoludely
1 month ago
Selected Answer: D
Having a hard time understanding why increasing inventory isn't the right answer
upvoted 1 times
absoludely
1 month ago
Nvm, figured it out.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago