Question #: 129
Topic #: 1
[All CSCP Questions]

Which of the following consequences is typical of a push-based supply chain?

  • A. Longer lead times
  • B. Higher product obsolescence
  • C. Lower economies of scale
  • D. Smaller production batches
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
BPIexam
4 months, 2 weeks ago
A. Longer lead times
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.