Question #: 533
Topic #: 1
[All CSCP Questions]

Which of the following risks poses the greatest threat for a make-to-order (MTO) company with a make-to-stock (MTS) supplier?

  • A. Inventory risk for the company
  • B. Inventory risk for the supplier
  • C. Debt leverage risk for the company
  • D. Debt leverage risk for the supplier
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Daesma
1 year, 4 months ago
Selected Answer: B
In an MTO model, the company manufactures products after receiving an order from the customer, which minimizes its inventory risk because it does not hold large quantities of stock. In contrast, in an MTS model, the supplier manufactures products to stock them in inventory in anticipation of future orders. This means that the supplier carries significant inventory risk, especially if demand for those products decreases or is uncertain.
upvoted 3 times
...
CSPark000
1 year, 5 months ago
Why not B ?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...