exam questions

Exam CSCP All Questions

View all questions & answers for the CSCP exam

Exam CSCP topic 1 question 651 discussion

Actual exam question from APICS's CSCP
Question #: 651
Topic #: 1
[All CSCP Questions]

A company's strategy is to position itself as a responsive supplier. Which lead time measurement would be most appropriate in supporting this strategy?

  • A. From order entry to order shipment
  • B. From customer quote to order acknowledgement
  • C. From order entry to customer receipt
  • D. From order shipment to customer receipt
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Shashak
Highly Voted 10 months, 3 weeks ago
option C
upvoted 5 times
...
Sam_malli007
Most Recent 2 weeks, 1 day ago
Selected Answer: C
*C. increasing process efficiency.** Increasing process efficiency often aligns with environmental responsibility because it typically involves reducing waste, optimizing resource use, and minimizing energy consumption. This approach not only supports sustainability goals but also often leads to cost savings and improved operational performance. While the other options might have some indirect benefits, they are not as directly aligned with environmental responsibility: - **A. Reducing the size of facilities** might reduce energy use but doesn't necessarily address broader environmental impacts. - **B. Reducing supply chain costs** could involve environmentally friendly practices, but it is not inherently focused on sustainability. - **D. Increasing product throughput** might lead to higher resource consumption and waste if not managed carefully, which could conflict with environmental goals.
upvoted 1 times
...
Rajiv8047
4 months, 2 weeks ago
Selected Answer: C
A responsive supplier is one that is able to quickly and efficiently meet the needs of its customers. This means that the supplier must be able to shorten its lead times, which is the time it takes to fulfill a customer order. The lead time measurement that best reflects the responsiveness of a supplier is from order entry to customer receipt
upvoted 3 times
...
[Removed]
7 months ago
Selected Answer: A
A is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago