A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied. Which date type would the project manager utilize?
B. Projected Date
Explanation:
Projected Date is used to estimate the likely completion date of a task based on its current progress and any dependencies or predecessors, without taking into account any task constraints. It helps to forecast when the task might realistically finish considering the work already completed and the ongoing progress.