A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.
Which date type would the project manager utilize?

  • A. Estimated Date
  • B. Projected Date
  • C. Planned Date
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
5c05494
4 days, 11 hours ago
Selected Answer: B
B. Projected Date Explanation: Projected Date is used to estimate the likely completion date of a task based on its current progress and any dependencies or predecessors, without taking into account any task constraints. It helps to forecast when the task might realistically finish considering the work already completed and the ongoing progress.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago