Exam AD0-E903 topic 1 question 35 discussion

Actual exam question from Adobe's AD0-E903
Question #: 35
Topic #: 1
[All AD0-E903 Questions]

A video designer is spending an excessive number of hours on a Project that involves editing a TV commercial. The tasks are keeping the designer from completing other assigned work. After discussing the matter with the designer, the project manager determines that the additional hours for this Project are necessary and suspects that the number of hours budgeted for the video designer’s time on this Project was too low in comparison to the actual need. The project manager will need data to illustrate the problem and potentially request more resources for this Project so that the designer can still meet commitments on other assigned work.
Which native Project tool is designed to illustrate data on how the Planned Hours for the video designer on this Project vary from the Actual Hours spent on the Project?

  • A. Utilization
  • B. Workload Balancer
  • C. Hours
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
5c05494
4 days, 19 hours ago
Selected Answer: C
C. Hours Explanation: The Hours tool in Workfront is designed to help project managers and teams track the Planned Hours versus the Actual Hours spent on a task or project. This tool allows for tracking how much time has been estimated for a designer (or any team member) and how much time they have actually spent on the task or project. It provides a clear view of whether the original estimates were accurate, and it helps identify when more resources or adjustments are needed. In this case, the project manager can use the Hours tool to compare the Planned Hours with the Actual Hours worked by the video designer, illustrating whether the initial allocation was insufficient.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago