exam questions

Exam AD0-E903 All Questions

View all questions & answers for the AD0-E903 exam

Exam AD0-E903 topic 1 question 28 discussion

Actual exam question from Adobe's AD0-E903
Question #: 28
Topic #: 1
[All AD0-E903 Questions]

A company expects managers to complete a Workfront Business Case and submit it to the Project Sponsor for approval before a project enters Planning status.
What Workfront process will effectively facilitate the Project Sponsor review?

  • A. Request Approval Process
  • B. Request Submission Process
  • C. Project Submission Process
  • D. Project Approval Process
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
5c05494
4 days, 22 hours ago
Selected Answer: A
A. Request Approval Process Explanation: In Workfront, the Request Approval Process is the process that can effectively facilitate a Project Sponsor's review. This process allows for formal approval to be requested from a designated approver, which, in this case, would be the Project Sponsor. When the business case is completed by the manager and submitted for review, the Request Approval Process ensures that the Project Sponsor can review the business case and formally approve or reject it before the project moves into the Planning status.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago